WHS project complete
By Brian Burns
Staff writer
Aside from a few
remaining punchlist items, the work on the Walpole High School
renovation and expansion project is all but finished.
For the first time
since 1998, school administrators kicked off a new school year last week
with the entire building at their disposal, including the new
auditorium.
For students and
teachers, the distractions and inconveniences that came along with the
project are now rapidly fading memories.
But there’s one part
of the project that still lingers – the legal battle among the
contractor, Bacon Construction of East Providence, the architect,
Drummey Rosane Anderson, Inc. of Newton (DRA), and the town.
All three parties have
filed breach of contract claims seeking monetary damages as a result of
the project, which dragged on for more than two years past its original
completion date.
The claims are filed in
Norfolk County Superior Court in Dedham.
Based on documents
filed in 2002, Bacon is seeking $414,165 in damages from the town for
costs incurred due to work acceleration and performing out-of-sequence
work.
Walpole’s
counterclaim against Bacon seeks $738,000 in damages for the delay in
completing the project, though it’s possible that the number has
changed since then as the delay continued well past the date that the
claim was filed.
Walpole is also seeking
an unspecified amount from DRA to cover the cost of defending itself
against Bacon’s claim and for defending itself against a state
handicapped access board in the spring of 2002.
DRA is seeking an
unspecified amount from Walpole for architectural services rendered.
No hearing date has
been set in the case.
Town Administrator
Michael Boynton said last week that the Permanent Building Committee has
been working hard to resolve the disagreements before the case reaches
the trial stage.
It’s in the town’s
best interest to settle the disputes amicably and avoid costly
litigation fees, he explained.
The $23 million high
school project broke ground in the summer of 1999. For the first few
years of construction, everything seemed to be moving along fairly well.
The first two phases of
the project were completed on or near schedule, and there was even some
hope that the third and final phase could be completed ahead of time.
Phase III called for
renovations to the "A" building of the high school, the
three-story wing facing Common Street that houses the English, social
studies and fine arts departments.
Renovations to that
wing, which was built in 1908, turned out to be the longest and most
complicated part of the entire project.
Phase III was
originally supposed to be completed in December of 2001. Administrators
didn’t get all three floors back until January of 2003, however. The
school auditorium didn’t come back until this summer.
Disagreements between
Bacon and DRA on how to proceed with the work in Phase III led to some
heated discussions before the Permanent Building Committee. The working
relationship between the three parties rapidly began to deteriorate.
According to documents
in court, the breaking point seems to have come in March of 2002, after
Bacon claims that DRA changed the plans for roof work in the A wing.
According to Bacon, the
change by DRA further delayed work on Phase III, which had already been
hindered by the architect’s failure to respond rapidly to previous
requests for information.
Bacon subsequently
filed a breach of contract claim against the town, alleging that Walpole
failed its responsibility to properly supervise the architect during the
construction phase.
Soon after Bacon filed
its claim, the town filed breach of contract claims against both Bacon
and DRA, claiming that both parties had failed to live up to their
contractual responsibilities.
The town seemed most
concerned that both Bacon and DRA had failed to identify and correct
areas of the high school that did not meet current accessibility codes.
DRA then filed its own
breach of contract claim against the town. Both Bacon and DRA name each
other as third party defendants in their claims against the town.
All of the claims were
filed in the spring and summer of 2002.
According to Bacon’s
original claim, DRA "continually failed to respond to requests for
information from filed subcontractors and Bacon regarding critical areas
of renovation work being performed at the site."
According to Bacon,
state law requires architects to respond to all requests for information
within 30 days or to provide a reason why that information can’t be
given in that time frame.
Bacon claims that in
many situations it took DRA between 75 to 120 days to respond to
requests for more information.
For instance, Bacon
claims that in July of 2001 it submitted shop drawings for ductwork that
was to be installed in the A building.
DRA returned the
drawings in August of 2001 with instructions to revise and resubmit,
according to the Bacon.
Bacon resubmitted the
drawings in September, but didn’t hear back from DRA until three
months later.
Then, in March of 2002,
Bacon claims that DRA redesigned the roof system for the first floor of
the A building – three months after the entire project was supposed to
be finished.
Bacon claims that the
redesign affected the ductwork plans that had been approved the previous
December, thus further delaying work on the project.
Bacon acknowledges that
the contract they signed with the town indicates that the company is not
entitled to damages for any delays in the project that are caused by
anyone, including the architect or the owner.
But Bacon points out
that the contract does say that in the case of delays, they would be
entitled to additional time to complete the project.
Bacon claims that it
repeatedly requested extensions for the project, which the town did not
grant.
By refusing to grant
any extensions, the town has essentially voided the "no damages for
delay" clause in the contract, according to Bacon.
The town’s
counterclaim to Bacon alleges that the contractor failed to properly
coordinate and supervise the work being done by subcontractors at the
site.
Bacon also failed to
ensure that the work was being carried out "without conflict and
delay," according to the town’s claim. Both were required of
Bacon under the terms of the contract.
The town also claims
that Bacon also failed to perform all construction work in compliance
with all applicable building codes and regulations, or to notify the
town of any portion of the contract documents that varied from those
codes.
Specifically, the town
claims that Bacon failed to realize and notify the town that the
exterior ramp in front of the high school did not meet accessibility
codes.
As a result of Bacon’s
failure to perform the work in accordance with those regulations, the
town incurred considerable expense and delay from the need to replace
that ramp.
The town’s major
claim against DRA is that the architectural firm failed to identify all
of the existing conditions at the high school in order to include all
essential work in the project’s specifications.
This includes failing
to identify the need for work on the gym ceiling and roof, failing to
identify that the school’s indoor ramps needed to be brought up to
current accessibility codes, and failing to properly design certain
items to meet code, such as the shower stalls in the gym locker rooms
and the gym bleachers, according to the claim.
After receiving a
complaint from a citizen access monitor, the Massachusetts Office of
Disabilities inspected the high school in the spring of 2002 and found
30 items that did not comply with state regulations.
On that list were
several items that had been improperly constructed by Bacon that DRA did
not promptly identify and order to be corrected, according to the town’s
claim.
This included the
interior ramps, shower stalls and bleachers, as well as the slope of the
front walkway, and the curb cuts on the school sidewalks and in the
parking lots.
According to the town’s
claim, town officials were advised by DRA to request variances for the
violations from the state Architectural Access Board.
This decision was based
on the DRA’s assertion that in many cases it wasn’t feasible to
comply, according to the claim.
After three days of
hearings, the AAB denied the majority of the town’s requests and
ordered the deficiencies to be corrected by June 1, 2002.
The town’s claim
alleges that despite repeated requests from town officials, the DRA did
not design the corrective work on time, thus making it impossible to
meet the June 1 deadline.
The town also claims
that on numerous occasions during the course of the project, DRA
representative Dominic Vecchione "failed to conduct himself in a
professional manner in dealing with representatives of the town and
Bacon, consistently failed to act in accordance with the approved
schedules, and failed to approve samples, schedules, shop drawings, and
other submissions in a timely manner."
DRA also failed to
exercise the "care and skill ordinarily required by architects and
engineers in discovering and promptly reporting to the town any
deficiencies in construction work," according to the claim.
The town is seeking
compensation from DRA for the cost of defending accessibility issues
before the AAB and the cost of defending against Bacon’s counterclaim.
In response to the
claims filed by Bacon, DRA denies that it failed to respond to specific
requests for information in a timely manner.
The firm specifically
denies Bacon’s charge that it took them 75 to 120 days to respond to
information requests.
The firm also denies
the timeline for their approval of the HVAC ductwork drawings as
outlined by Bacon in its complaint, and denies making changes to the
roofing plans for the A building as described by Bacon.
DRA also denies that
Bacon built the handicapped access ramp according to the plans and
specifications.
In response to the
claims filed by the town of Walpole, DRA denies that it failed to
properly design the items found in violation by the AAB.